NW Tyler Street Reconstruction Project
  • Home
  • About The Project
  • Project Updates
  • Design Plan Sheets
  • Links
  • Contact
Select Page

Kansas Gas Service/NPL has completed their utility line crossing at Lyman Road and Lyman is back open to traffic.  Kansas Gas/NPL will be finishing their gas service main and service connections for the project the week of March 1-5.  Tyler Street will be open to two-way traffic from March 6 until the water line relocation work starts in mid-April

by sproutweb | Mar 2, 2022 | Update

Phase 1 of the NW Tyler Street project is currently advertised to contractors with a bid date of January 5, 2012.

by sproutweb | Jan 5, 2022 | Update

The design of the NW Tyler – Phase 2 Project from NW Beverly Street to NW Paramore Street is 90% complete. The Tyler Phase 2 project is currently scheduled for construction in 2025.

by sproutweb | Dec 22, 2021 | Update

The City of Topeka was awarded a federal Transportation Alternative Grant for a 10’ Concrete Shared Use Path on the east side of Tyler from NW Paramore Street to NW Lyman Road. This work will be designed as a separate KDOT project and is approximately 50% complete. The 10’ Shared Use Path construction is scheduled for 2023.

by sproutweb | Dec 22, 2021 | Update

Evergy, Cox Communications, and AT&T have relocated their utilities for Phase 1 of the project. Kansas Gas continues to relocate their main and road closures of NW Tyler will occur during this private gas main relocation work.

by sproutweb | Dec 22, 2021 | Update