Phase 1 of NW Tyler Street from Lyman Rd. to Beverly St. is substantially complete but will continue to be periodically closed to through traffic during working hours as the Contractor completes remaining punch list items for the project. It is expected the road will be open to unrestricted traffic on January 20, 2023.

Phase 2 of the project which includes reconstruction of NW Tyler from Beverly St. to NW Paramore will begin in March 2023. This project will also include construction of a 10-foot Concrete Shared Use Path on the east side of Tyler from Paramore to Lyman Rd. Traffic will continue to be impacted on NW Tyler during these projects. Updates for the Phase 2 project will continue to be posted throughout 2023.