“The Contractor will be moving to the final phase of NW Tyler Rd. Reconstruction Project this week between NW Waddell and NW Beverly St. The Contractor will be constructing temporary access roads for local access and removing pavement. While they begin this phase of construction, the Contractor will be finishing up sidewalks and driveways on the newly reconstructed phase of NW Tyler between NW Paramore and NW Waddell St.
The KDOT Shared Use Path project on the east side of NW Tyler from Beverly to Lyman Road is substantially complete and final seeding will be placed within the next week. The remainder of the Shared Use Path Project from Beverly to Paramore will resume upon the completion of the road project which is expected to be completed in December of this year.
Through traffic should continue to use the existing NW Topeka Blvd. detour route until the road project is complete.”