NW Tyler Street Reconstruction Project
Project Updates
Phase 1 of NW Tyler Street from Lyman Rd. to Beverly St. is substantially complete.
Phase 1 of NW Tyler Street from Lyman Rd. to Beverly St. is substantially complete. Final punch list items, final grading, and final seeding is expected to be completed by the end of March. Phase 2 of the project which includes reconstruction of NW Tyler from Beverly...
Phase 1 of NW Tyler Street from Lyman Rd. to Beverly St. is substantially complete
Phase 1 of NW Tyler Street from Lyman Rd. to Beverly St. is substantially complete but will continue to be periodically closed to through traffic during working hours as the Contractor completes remaining punch list items for the project. It is expected the road will...
Starting Wednesday, November 9, NW Tyler will be open to traffic from Lyman Rd. to Williams St.
Starting Wednesday, November 9, NW Tyler will be open to traffic from Lyman Rd. to Williams St. NW Tyler from Williams St. through Waddell St. will remain closed for road construction, gas main, and water service relocation work. NW Paramore east of Tyler and NW...
Starting Wednesday, October 12, the contractor will begin removing pavement and excavating for the new pavement on NW Tyler between NW Ross and NW Beverly.
Starting Wednesday, October 12, the contractor will begin removing pavement and excavating for the new pavement on NW Tyler between NW Ross and NW Beverly. Local residents will continue to have access to their driveways from the Tyler St. Right-of-Way. NW Tyler from...
NW Paramore St. just east of NW Tyler street will be closed starting Friday, October 7 for water main installation.
NW Paramore St. just east of NW Tyler street will be closed starting Friday, October 7 for water main installation. The northbound lane of NW Tyler will also be closed at NW Paramore for this work. Residents and businesses between NW Paramore and NW Ross St. should...

NW Proctor St. west of NW Tyler St. will be closed the morning of 9/29/2022 for storm sewer installation
NW Proctor St. west of NW Tyler St. will be closed the morning of 9/29/2022 for storm sewer installation. NW Beverly between Tyler and Taylor remains open to two-way traffic. NW Waddell west of NW Tyler remains closed for water line installation. NW Tyler between NW...