The intersection of NW Tyler and Paramore has been constructed and will be open to traffic on Friday, May 12.    

The Contractor will be constructing temporary access roads from Paramore to Waddell this week and will be removing pavement on Tyler after temporary access roads have been constructed for residents and business along this section of the project.  

It is anticipated that the Tyler reconstruction from Paramore to Waddell will take approximately 6 weeks, weather permitting.  Upon completion of Tyler from Paramore to Waddell, the contractor will construct temporary access roads and remove and reconstruct Tyler from Waddell to Beverly.  The contractor may begin storm sewer work on Waddell and Beverly from Tyler to Polk prior to reconstruction of Tyler north of Waddell.